If something goes wrong
If it is late
If the builder does not hand over the flat by the date in the agreement, you can either withdraw from the project and ask for all you paid back, with interest and compensation, or stay in the project and get interest for every month of delay until possession. The rate is SBI's highest MCLR + 2%; a refund is to be paid within 90 days of falling due. If the builder does not pay, complain to TG RERA.
TG RERA complaints portal
📞 04029394973If it is rejected
The builder may cancel your allotment only as the agreement for sale allows. If the cancellation is one-sided, without sufficient cause and against the agreement, you can approach TG RERA.
TG RERA complaints portal
📞 04029394973If you are asked for more money
If the builder takes more than 10% of the price without a registered agreement, you can complain to TG RERA online, or on paper in Form M or Form N.
TG RERA complaints portal
📞 04029394973Also
The builder may not change the sanctioned plan, specifications or fittings of your flat without your consent (minor changes have their own rules). Changing the plans of the building or the common areas needs the written consent of at least two-thirds of the buyers. If this is not followed, complain to TG RERA.
TG RERA complaints portal
📞 04029394973Also
If the builder does not put right a defect you reported within 30 days, you are entitled to appropriate compensation. Complain to TG RERA.
TG RERA complaints portal
📞 04029394973Also
For questions, the TG RERA office: DTCP Building, Ground Floor, Masab Tank, Hyderabad; Monday to Saturday, 10:30 AM to 5:00 PM.